Cebu PMIS > Project Tasks > Complete structural building works  

Project Tasks: Complete structural building works

The content of this item will be sent as an e-mail message to the person or group assigned to the item.

Title

Complete structural building works 

Duration

50 

Start Date

4/20/2009 

Finish Date

6/11/2009 

Baseline Start

4/20/2009 

Baseline Finish

6/11/2009 

Assigned To

 

Task Status

Not Started 

% Complete

 

Description

 

Priority

(2) Normal 
Attachments
Created at 11/4/2008 12:53 PM  by Dux Raymond Sy 
Last modified at 11/4/2008 12:53 PM  by Dux Raymond Sy